Westmont's months-long reconstruction of E. Des Moines Street is wrapping up, with final paving work scheduled for Saturday, Nov. 21.

Crews planned to apply tack coat early that morning and then lay the surface course of asphalt, weather permitting, according to the village's project page. The village advised residents to watch for "Fresh Oil" signs and use caution driving through the area. Residents who did not want to drive through fresh oil could park on adjacent streets overnight.

The project covers E. Des Moines St. between S. Cass Ave. and S. Richmond Ave. The segment between S. Cass Ave. and S. Warwick Ave. is being resurfaced. East of S. Warwick Ave., the road is being fully reconstructed with new curbs and an upgraded stormwater collection system.

Through-traffic has been prohibited during construction, though driveway access has been maintained for residents.

Months of work

Construction officially began Sept. 4, 2026, after Schroeder Asphalt was awarded the contract in late June. The village had estimated a summer-to-fall 2026 timeframe for the project.

Storm sewer installation came first, running through early October. Crews then moved to excavation, rough grading and concrete curb and gutter work in late October. A Nov. 16 update said crews were finishing the stone base and paving the first layer of asphalt that week, with the final layer scheduled for the following week.

The village sent three letters to affected residents over the course of the project, starting July 27.